No matter what, all of our cabinets meet a minimum quality that includes solid wood cabinet box construction and soft close features.
Weather its our best priced cabinets or full custom, we will provide value!
Lead time for special order cabinetry can range from 4 weeks to 8 weeks depending on the brand.
Cabinet demolition and installation can be as little as 3 days! We install half inch plywood and a temporary sink to give you a functional kitchen while awaiting your custom countertop.
Our installation comes standard with a high-quality leveling system that leaves the base cabinets laser level perfect for added countertop integrity.
We provide a laser templating service.
Lead times for countertop install after template are about 6 weeks.
A We Love to Remodel team member will be there for the template and install to make sure the process goes smoothly.
Need some ideas, check out beautiful quartz we offer in our Online Lookbook! We also work with Cambria!
Tile is an art! We take the time your product deserves to ensure a high quality result.
We love installing Schluter products giving you waterproofing that lasts a lifetime! We can also offer in-floor heating and curbless showers!
Start brainstorming online with Floor & Decor offering top quality products at rock bottom prices!
All tile installation will take a minimum of 2 days; larger projects like a custom tile shower will often add week(s) to the project.
Thinking about something other than tile flooring? We offer the highest quality Luxury Vinyl Plank product and installation.
New trim is included as well to cover the gap necessary between the new flooring and walls. Unlike flooring-only companies, we are the carpenters on staff!
With floor leveling and new trim, average flooring projects typically take 3 days.
Check out some of the latest LVP designs online with Flooret.
Full Kitchen Remodel
- Demolition (average 1/2 day)
- Wall Reconstruction--not always needed (avg. 1/2 day)
- Drywall (avg. 3 days)
- Cabinetry Install (avg. 2 days)
- Countertop Templating (usually last day of cabinet install)
- Temporary Sink and Countertop Install (usually last day of cabinet install)
**at this point, your kitchen is back to functional**
- Countertop Install (avg. 2 hours)
- Backsplash (avg. 2 days)
- Final Touch-Ups (avg 1/2 day)
Full Gut Bathroom Remodel
- Demo (avg. 1/2 day)
- Wall Reconstruction--not always needed (avg. 1/2 day)
- Drywall (avg. 3 days)
- Vanity & Top Install (avg. 1/2 day)
- Floor & Trim Install (avg. 1 day)
- Tile Work (avg. 5 days)
- Final Touch-Ups (avg 1/2 day)
Allegan, Barry, Clare, Clinton, Eaton, Gratiot, Ingham, Ionia, Isabella, Kent, Lake, Mecosta, Midland, Montcalm, Muskegon, Newaygo, Oceana, Osceola, Ottawa, Saginaw, Shiawassee